Note 41 — Chapter III · Plans Are Made and Forces Are Readied
Reading edition
The supplies required for the operation involved staggering quantities. For an invasion force of 150,000 men, the War Department figures showed that, for the landing period alone, 1,500,000 tons of general equipment, 235,000 tons of combat vehicles, 200,000 tons of ammunition, and 200,000 tons of medical supplies were required. Thereafter, 332,000 tons of equipment would be required every thirty days.41 According to the final plan, issued by General Krueger on 30 September 1944,42 the units of the Sixth Army, X Corps, and Sixth Army Service Command, under General Casey, which were to arrive at Leyte between 20 and 30 October were to take ashore a minimum of ten days’ supply of all classes (except engineer supplies, which were to be for at least thirty days), and two units of fire.43 In this way the strain on ASCOM supply units would be lessened, and ASCOM, it was hoped, would have time to establish dumps and make the necessary supply installations. In addition to supplies accompanying the assault troops, sufficient quantities were to be brought into Leyte by 30 October to bring the total supplies for the troops to the following figures, expressed in days: thirty days of food, clothing, and equipment; fifteen days of motor transport fuel and distillate; and thirty days of other petroleum products. There were also to be five units of fire for combat troops and three for service troops. The original plan had called for a thirty-day supply of all petroleum products to be brought in by A plus 10, but this quantity was reduced when General Krueger adopted a plan for the installation by A plus 7 of bulk fuel storage. The XXIV Corps supply levels were to remain the same as those planned for the now-canceled Yap operation, since the corps was already loaded with supplies which were considered adequate for the Leyte invasion.44