Much ingenuity was exercised by the engineers in overcoming difficulties. In enlarging the Tacloban airstrip, one of the greatest impediments to progress was the limited supply of coral for surfacing the runways. The engineers conceived the idea of having the dredge Raymond, which had been brought forward to dredge the navigational channel, used to pump coral from the channel bottom onto the runways. The 2,800-horsepower pumps could transport solid matter one mile through pipes that extended across the bay and onto the land, and they could also raise the dredged matter as much as 300 feet above sea level. The engineers found that this pipeline was the quickest way to transport material to the Tacloban airstrip, though mechanical difficulties sometimes developed.15