Chapter VII · Estimating

Reading edition

74. Methods of Estimating.—Building costs may be divided into two main divisions, cost of material and cost of labor. There is but one so-called safe way to figure or estimate the cost of any particular piece of carpentry work. This consists in "taking off" the material quantities in detail and to this adding the labor cost of placing the same. This is the method in common use by contractors in making a final estimate. Where a rough or working estimate is required, such as an architect's estimate of the probable cost of a building planned by him, two methods may be used. One consists in figuring the cubical contents in feet and multiplying a predetermined, or unit price per cubic foot for that type of house. Ordinarily, the main frame is figured, counting from the basement floor to the top of the attic walls that are, or may be finished—outside measurements. Porches and open spaces are not figured. A second method consists in estimating the number of squares (100 sq. ft.) of side wall, of partitions, of floors, etc., and multiplying a predetermined price per square for a similar type of building. This latter method is more accurate than the cubic-foot unit method.

75. Table for Estimating by Cubic-Foot Unit.—The following table of unit prices will give a rough working estimate for various types of building differentiated after the custom of insurance adjusters. The prices are for 1915 and to be of any value must be compared with known costs of similar structures in the community in which they are to be used. Any evident variations in unit costs so discovered should be noted and corrections made.

Explore with AITake your curiosity a little further.

Reading settings