Note 81 — Chapter VII · RAILWAY BRIDGES AND VIADUCTS.
Reading edition
During the construction of the bridge a part of the crown of the eastern arch proved defective, in consequence of the cement in the middle of the brickwork not having set sufficiently at the time when the centering was eased. Apprehensions which had been entertained by some as to the safety of the structure were groundless, for when the defective part was taken out and replaced, no further trouble was experienced. The bridge has stood well, and has shown none of those symptoms which an overstrained structure exhibits.