Note 37 — Chapter II · THE CLIFTON SUSPENSION BRIDGE. A.D. 1829—1853. ÆTATIS 24—48.
Reading edition
Some re-arrangement of Mr. Brunel’s design was rendered necessary in order to adapt the Hungerford bridge chains to the Clifton bridge, and there are three chains instead of two, as in Mr. Brunel’s design. The platform is stiffened by wrought-iron girders instead of by timber trussing, and the whole bridge is stiffened transversely by the wrought-iron girders at the sides, which are connected throughout by diagonal bracing. The clear width of the bridge is 30 feet, 5 feet less than originally intended. It should be added, that no attempt has been made to complete the towers according to Mr. Brunel’s architectural designs.