Note 178 — Chapter XIV · DOCK AND PIER WORKS. A.D. 1831—1859. ÆTATIS 26—54.
Reading edition
It may be desirable to give a short explanation of these works, which consisted principally of a sluice, a trunk, and a drag-boat.
The Sluice was made in the abutment of Prince’s Street Bridge, and was intended to create a scour after the water had been let off from either side of the float, the opening at the bridge being closed by a caisson which had long been in use when (as was formerly the case) the upper part of the float was scoured through Bathurst Basin.
The Trunk, near the entrance from Cumberland Basin, is a wooden culvert between the floating harbour and the river. As much of the mud as could be dragged there was deposited at the entrance of the trunk, and, when the tide was low in the new channel of the Avon, sluices were opened, and the water rushed through from the floating harbour, carrying the mud with it.
The Drag-Boat was fitted with a steam-engine which worked a large windlass with three compartments, round two of which chains were passed and fixed to posts on the quays, and the boat was dragged backwards and forwards. The third compartment of the windlass worked a chain which elevated or depressed a scraper, attached to a long pole at the stern, and secured from swerving by a chain-bridle which passed under the boat. The scraper stirred up the mud, and deposited the more solid parts at the entrance of the trunk.
Mr. Brunel also desired that the float boards of the Neetham Dam should be put into proper working order; and that they should be altered so that, in times of land floods, the whole or a considerable portion of the excess of water should be retained, and passed through the feeder; and that even the water of spring tides should be allowed to pass the dam, and then be stopped back for the same purpose.