Note 24 — PART I SPECIFICATIONS FOR STREET ROADWAY PAVEMENTS

Reading edition

The importance of proper and thorough rolling is not usually fully appreciated, and this part of the work is often shirked by the contractor. Not only should the heavy roller be at work as soon as the material will bear it, but the roller should, when work is progressing regularly, be kept at work all the time. It is a safe motto that the final rolling cannot be overdone.