Note 35 — PART I SPECIFICATIONS FOR STREET ROADWAY PAVEMENTS (continued 2)
Reading edition
The practice of filling the joints with gravel to a depth of one inch or more before the blocks are rammed is of doubtful utility. If the blocks are set closely against each other they will be well held in place while the ramming proceeds. In practice it is hardly possible to closely gage the depth of such preliminary gravel filling, and the top or final filling whether of grout or of gravel and bituminous cement, is likely to vary greatly in depth, and the lateral support of the blocks is thus likely to vary in strength and rigidity.