The Governor plainly illustrated this device. The engineer having estimated the amount of work and materials, the bidders added their prices.

A bid as follows:

100 cubic yards of vertical wall, at $3$300.00

3,855 cubic yards of slope wall, at $1.50 5,782.50

2,400 feet B.M. white oak, at $50 120.00

60,000 feet B.M. hemlock, at $15 900.00

Total estimate of A$7,102.50

B bid as follows:

100 cubic yards of vertical wall, at $6$600.00

3,855 cubic yards of slope wall, at 30 cents 1,156.50

2,400 feet B.M. white oak, at $70 168.00

60,000 feet B.M. hemlock, at $3 180.00

Total estimate of B$2,104.50

B was given the contract as the lowest bidder, after which the work was changed as follows:

3,955 cubic yards of vertical wall, at $6$23,730.00

62,400 feet B.M. white oak, at $70 4,368.00

Actually paid B by the State$28,098.00

On ten of these contracts, originally amounting to $424,735.90 the State paid $1,560,769.84.—Tilden's Public Writings and Speeches, Vol. 2, pp. 106-108.